The bill for a council’s plan to improve its headquarters has increased by £301,000 because of rising construction costs.

Labour-run Bassetlaw District Council has approved the extra funds as it progresses with improvements to its Queen’s Buildings home.

The Worksop building, which also hosts the police and a Job Centre branch, is due to benefit from nearly £2.4m of decarbonisation works.

Hide Ad
Hide Ad

The funding will come from Government grants rather than local council tax.

Bassetlaw District CouncilBassetlaw District Council
Bassetlaw District Council

These are works to reduce the carbon emissions of public buildings and improve the energy footprint, while also including measures to save on bills.

The works will include fabric improvements and a new heating system, bringing forward “large cost savings for operation and future maintenance”.

It comes as part of the Government’s Public Sector Decarbonisation Scheme.

Hide Ad
Hide Ad

It is expected to save the council as much as £50,000 per year and also “shield” the building from future energy price increases.

A new roof is also due to be installed on the building, with the current roof “a decade or more beyond its guaranteed life expectancy”.

Read More
14 Bassetlaw restaurants, cafes, pubs and takeaways given new five-star food hyg...

This had not initially been planned but the authority says the new roof – which will include solar panels – will also help to bring further savings.

“While in good condition, it will be better to insulate and renew the roof before a leak or issue is evident, especially with the heat pumps and solar panels being installed across its surface,” the council said.

Hide Ad
Hide Ad

The first phase of the scheme was initially expected to cost £1.398m but has since risen to £1.699m, meaning an extra £301,000 is needed.

The funds will be found through unallocated New Homes Bonus grants.

The council says the increases are due to a 30 per cent rise in construction costs “most notably from supply shortages”.

The contractor initially appointed to conduct the work also ceased trading in September, meaning a new one had to be found.

Hide Ad
Hide Ad

There were also “complications with missing documentation from the council’s files”, the authority adds.

A council report said: “Through fabric improvements and a new heating system, this project will induce large cost savings for operation and future maintenance at Queen’s Buildings.”