Turbines arrive at Ulley wind farm

Turbine blade delivery

Turbine blade delivery

COMPONENTS which will make up the Penny Hill wind farm at Ulley are beginning to arrive on site.

Barlborough-based Banks Renewables began preparatory work on the wind farm in July last year and despite the wet weather, work has progressed on schedule.

The steel tower sections for the turbines are currently being built at the Mabey Bridge factory in Chepstow. The first component deliveries began last week and will continue for around three weeks.

It is expected that the testing and commissioning phase of the project will be completed in the spring of this year.

Phil Dyke, development director at Banks Renewables, said: “Our Penny Hill delivery schedule has been carefully designed to minimise any traffic disruption, and Banks has been working with the local authorities, the police, the Penny Hill community liaison committee and people living in the immediate vicinity to ensure everyone will be kept up to date on when deliveries are scheduled to take place.”

“We’re using our best endeavours to make these deliveries with minimum disruption to traffic in local communities, and are looking forward to starting to generate safe, clean and sustainable energy at Penny Hill in the very near future.”

“The wind farm is already making a positive contribution to the local area in several different ways, including new jobs, supply chain support and the Warm Zone scheme, and with regular funding from the wind farm’s benefits fund still to come, this is just the beginning of the long-term, positive impact that our work here will have on the local community.”

As part of the scheme Banks has set up a fund worth around £20,000 a year - £500,000 across the 25 year lifespan of the wind farm - will enable the company to deliver a range of community and environmental improvements in partnership with local people. The first part of funding is set to become available this summer.

Banks agreed to distribute a notification of the key traffic dates and to implement an email alert service to minimise any traffic disruption caused by the component deliveries. Anyone wanting to sign up to this service should email pennyhill@banksgroup.co.uk.


 
Find It

"Business owner? - Claim your business and Advertise with us"

In association with qype logo

Looking for...

Featured advertisers

Jobs

Search for a job

Motors

Search for a car

Property

Search for a house

Weather for Worksop

Monday 20 May 2013

5 day forecast

Today

Cloudy

Cloudy

Temperature: 10 C to 20 C

Wind Speed: 10 mph

Wind direction: North

Tomorrow

Cloudy

Cloudy

Temperature: 7 C to 14 C

Wind Speed: 10 mph

Wind direction: North

Press Complaints Commission

This website and its associated newspaper adheres to the Press Complaints Commission’s Code of Practice. If you have a complaint about editorial content which relates to inaccuracy or intrusion, then contact the Editor by clicking here.

If you remain dissatisfied with the response provided then you can contact the PCC by clicking here.

Worksop Guardian provides news, events and sport features from the Worksop area. For the best up to date information relating to Worksop and the surrounding areas visit us at Worksop Guardian regularly or bookmark this page.